Bhubaneswar Metro Train Soil Testing Initiates for Determined 26 km Route
Soil Testing Phase:
Soil testing process has started for Bhubaneswar metro train project. In phase 1, 26 km metro train route is planned, soil testing process has started from Nandankanan road later on which will go up to Biju Patnaik airport for soil test.
Lab Testing Report:
This test shows how far this soil is useful for the metro train project. For this test, the soil is collected at a distance of 1.5 meters for test. The soil will be tested in the testing lab which is located in Odisha and outside Odisha. The report from the testing lab will come in 3 WEEKS.
Detailed Project Reports (DPR) Submit:
GEOTECHNICAL investigations, the soil is extracted from a depth of 30 meters. After this, the TOPO survey will be conducted and then the EIS survey will be conducted. After receiving all the reports, Detailed Project Reports (DPR) will be compiled.